CONTEXT                                                decarbonization of heat in larger buildings such as
                                                       leisure centres. It also encouraged the DCC to be more
Public sector buildings must improve direct energy     ambitious with projects to meet these targets. The
performance between now and 2030 to meet the 2030      Gap to Target analyses revealed that there are a small
emissions reductions targets set out in the Climate    number of large buildings including DFB Fire Stations
Action Plan 2023, which include:                       which have the most impact on the emissions.

    51%  CO2 reduction                                 The DeliveREE Building Decarbonisation strategy
                                                       helps to determine when it is suitable to use Energy
    50%  energy efficiency improvement                 Performance Contracting (EnPC). When considering
                                                       upgrading a building the first consideration is deep
    90%  overall contribution from renewable           retrofit which generally means turning the whole
         space heating (heat pumps,                    building or part of, into an unoccupied space, i.e.
         biomass and district heating)                 a building site. If this is acceptable then the project
                                                       will follow the fabric first approach and traditional
    B BER rating of B                                  project development structures (similar to new build).
                                                       In Codema’s experience and from consulting EnPC
A Detailed Gap to Target assessments were              market stakeholders, the decision to decant a building
performed for Dublin City Council based on updated     and turn it into a building site will normally be driven
government 2030 targets. These targets focus on the    by many other factors other than energy or CO2
reduction of direct emissions, and this resulted in a  savings concerns, and environmental concerns alone
greater focus within the decarbonisation pathway on    are unlikely to be enough. So, if a building is not at
                                                       the stage in its life where deep retrofit is the obvious
                                                       choice, then the alternative is Decarbonisation.

72                                                     Bhriogáid Dóiteáin Bhaile Átha Cliath DUBLIN FIRE BRIGADE
   67   68   69   70   71   72   73   74   75   76   77